Potable Water Project Nears Completion

Published on June 05, 2023

gold fire hydrant

The potable water infrastructure build-out is near completion. The next step is to convey properties over to the Miami-Dade County Water and Sewer Department (WASD). The next two phases to be conveyed are 3A and 3C.

Seven of the 16 project sub-phases have been conveyed to WASD, representing 47% of the project. The Village Public Works office notifies residents once a conveyance has been made and provides step-by-step instructions on how to obtain potable water from WASD.

To convey the property to the county specific tasks must be completed. They include flushing the line, a pressure test, a bacterial test and restoration of the road and swale areas that were affected by the infrastructure build-out. 

The Village expects all project phases to be conveyed to the county by July 2023. The project began in January 2022. 

 

For more information about the project visit www.pinecrest-fl.gov/water.